Inception of EcoClean Technology Sdn. Bhd.

EcoClean Technology Sdn. Bhd. was established to improve the quality of water in rivers and water bodies. It also stops water pollutions caused by aggressive land development. CDS technology was introduced at the time of the Clean River Campaign and frequent flash floods in the Kuala Lumpur City due to blocked drains.

2000
G6 CIDB Contractor

EcoClean Technology Sdn. Bhd. is able to execute projects not exceeding RM10,000,000.

2000
Continuous Deflection Seperation (CDS) License

Obtained license to supply and install CDS Gross Pollutant Trap

2000
Aus-industry Emerging Industries Award

For continued focus on innovation and technological growth, this award recognises Continuous Deflection Seperation (CDS) as a rapid technological development in the industry.

2001, 2002
Deloitte Technology Fast 50 Award

This award recognises companies that have accelerated innovation and growth in developing proprietary technology or manufacturing a technology-related product.

2010
Ausdrain EnviroModule & Drainage Sole Distributor

Obtained sole distributorship to supply and install Ausdrain Enviromodule for rainwater harvesting, on-site detention and Drainage Cell

2014
Cleansall License

Obtained license to supply and install Cleansall Gross Pollutant Trap

2016
Vydro Soiless Green Wall Distributor

Obtained distributorship to supply and install Vyrdro Soiless Green Wall for vertical gardens under Empire Green

2016
E/One Low Pressure Sewer (LPS) System Sole Distributor

Obtained sole distributorship to supply and install E/One LPS system for sewer systems

2017
Bio Ultra Violet (UV) Sole Distributor

Obtained sole distributorship to supply and install Bio UV system for water treatment systems

2017
SME 100 Award 2017

This award recognises Malaysia’s fast-growing companies with key success factors

2018
SME Icons Recognition

This award recognises our Managing Director, Mr Yale Wong for outstanding contributions toward innovative, articulative and motivative actions that drive the industry and place Malaysia on the world map

2021
G7 CIDB Contractor

EcoClean Technology Sdn. Bhd. is able to execute projects without a tender capacity limit

2022
Admission as Member of Board of Governors for Infrastructure University Kuala Lumpur

Our Deputy Chairman, Dato’ IR Lim Chow Hock was admitted as a Member of Board of Governors

Project Milestones

2023
Syarikat Perumahan Negara Berhad, Johor

CDS P2018 2 units installed

2023
SUKE Highway, KL

EcoSac 1025 2 units installed

2022
Majlis Bandaraya Johor Bahru, Johor

CDS P3030 1 unit, CDS P2028 3 units installed

2022
Majlis Bandaraya Seberang Perai, Penang

CDS P2028 1 unit, CDS F0912 2 units installed

2022
Intan Baiduri, KL

EcoSac 1025 1 unit, EcoSac 0510 4 units installed

2022
Intan Baiduri, KL

EcoSac 1025 8 units installed

2022
Perdana Park City, KL

EcoSac 0510 8 units installed

2022
Robert Bosch Factory, Penang

CDS F0912 2 units, CDS F0908 1 unit installed

2021
Tiongnam Sullage Water Treatment Plant, Kuala Lumpur

CDS F1518 3 units installed incorporated with CDS Hybrid Clarifier at the treatment plant to achieve River Water Quality Class 2A

2021
MRT GPT 6, Sungai Gasi

CDS P2028 Twin 2 units installed

2021
MRT GPT 4, Sungai Gasi

CDS P2028 1 unit installed

2020
Bandar Serai Pond 5, PJ

CDS P2028 1 unit, CDS P2018 1 unit, CDS P2028 Twin 1 unit installed

2019
Parlimen Malaysia OSD 1

OSD Tank with capacity of 1647m3

2019
Taman Tasik Permaisuri

CDS F0912 1 unit installed

2018
Parlimen Malaysia OSD 2

Designed and built OSD Tank with capacity of 757m3

2016
Pahang Technology Park

CDS P2018 3 units, CDS F1512 2 units installed

2016
River of Life, Sungai Batu Pakej 1

CDS P3030 2 units, CDS P2028 1 unit installed

2016
Precint 17 & 19, Putrajaya

CDS F1518 1 unit, CDS P1015 1 unit installed

2015
Raffles American School, Johor

CDS P2028 1 unit, CDS P2018 twin 2 units, CDS P1518 1 unit, CDS F0912 2 units installed

2015
Precint 5, Putrajaya

CL900 1 unit, CL750 3 units installed

2015
Data Centre & Office, Shell Brunei

Designed and built OSD Tank with capacity of 15m3

2014
High End Bungalows, Damansara Height

Designed and built Rainwater harvesting system with capacity of 4.5m3 per unit

2014
Balai Bomba & Penyelamat Bandar Tun Razak

Designed and built OSD tank with capacity of 42m3

2013
River of Life, Sg Klang Pakej 4

CDS P2028 5 units, CDS P1012 14 units, CDS F0908 27 units, CDS P1009 4 units, CDS P1015 1 unit installed

2013
River of Life, Sg Keroyong

CDS P1009 12 units installed together with 2 years of maintenance

2013
Sg. Melaka

CDS P0708 4units, CDS P1009 2 units, CDS P1015 2 units, CDS P2018 1 unit installed

2011
Medini Iskandar, Johor

CDS P3030 twin 1 unit, CDS P3018 twin 2 units, CDS P3018 1 unit, CDS P2018 twin 4 units, CDS P2018 8 units, CDS P1015 3 units, CDS P1012 2 units, CDS P1009 2 units, CDS F1012 2 units, CDS F0908 7 units installed

2011
Universiti Malaysia Terengganu

Designed and built OSD tank with capacity of 221m3

2010
Universiti Tun Hussein Onn, Johor

Designed and built OSD tank with capacity of 226m3

2006
Precint 14, Putrajaya

CDS P2028 twin 1 unit, CDS P2018 1 unit installed

2004
Nottingham University, Broga

CDS P1015 2 units, CDS P2018 1 unit installed

2003
Precint 3, Putrajaya

CDS P1009 31 units, CDS P1012 10 units, CDS P1015 2 units installed

2003
Bandar Botanic Klang

CDS P0908 4 units, CDS P0912 13 units installed